| Variation | Contract Item | Description | Tender | Actual | Variance | Status |
|---|---|---|---|---|---|---|
| VS-SRV-001 | 5.1-1A.7.2 | Additional Monitoring Scope (Metric Survey) | $33,570.00 | $127,496.38 | $93,926.38 | Submitted |
| VS-SRV-002 | 5.1.1A.7.1 | Proportional Survey Scope Increase (RF Sons) | $47,565.00 | $87,995.25 | $40,430.25 | Submitted |
| TOTAL VARIATIONS | $81,135.00 | $215,491.63 | $134,356.63 | |||
VS-SRV-002: Proportional increase based on EW-11A (Piling +26%) and EW-31 (Temporary Retention +143%) - Blended multiplier 1.85x
| Category | Description | Amount | % |
|---|---|---|---|
| Monitoring - Daily | Track, platform, sleeper monitoring, reporting | $104,259.75 | 82% |
| Monitoring - Setup | Installation of brackets, magnets, baseline observations | $16,387.50 | 13% |
| Materials | Magnets, L brackets, stickers, glue | $6,849.13 | 5% |
| ACTUAL COST TO DATE | $127,496.38 | ||
| 0% | |||
| 0% | |||
| 0% | |||
| TOTAL COST (Actual + Forecast) | $127,496.38 | 100% | |
| Less: Tender Allowance | ($33,570.00) | ||
| VARIATION CLAIMED | $93,926.38 | ||
| Component | Reference | RFT Basis | Actual/IFC | Increase |
|---|---|---|---|---|
| Piling Works | EW-11A | 102 piles | 129 piles | +26% |
| Temporary Retention | EW-31 | $660,584 | $1,603,118 | +143% |
| Calculation | Factor | Amount |
|---|---|---|
| Original Tender Allowance (Item 5.1.1A.7.1) | 1.00 | $47,565.00 |
| Piling Multiplier (50% weighting) | 1.26 | - |
| Temp Works Multiplier (50% weighting) | 2.43 | - |
| Blended Multiplier | 1.85 | - |
| Adjusted Survey Budget | $47,565 x 1.85 | $87,995.25 |
| Less: Original Tender Allowance | ($47,565.00) | |
| VARIATION CLAIMED | $40,430.25 |
This section tracks actual survey and setout costs incurred. Use the forecast fields to estimate remaining costs.
| Category | Amount |
|---|---|
| Pile Setout | $15,973.00 |
| Site Establishment | $4,313.75 |
| Processing / Admin | $4,136.25 |
| Metric Subtotal (To Date) | $24,423.00 |
| Metric Total (Inc. Forecast) | $24,423.00 |
| Category | Amount |
|---|---|
| Setout Files | $20,887.30 |
| Column/Bolt Checks | $1,140.70 |
| Monitoring | $651.10 |
| RF Sons Subtotal (To Date) | $22,679.10 |
| RF Sons Total (Inc. Forecast) | $22,679.10 |
| Subcontractor | To Date | Forecast | Total |
|---|---|---|---|
| Metric Survey | $24,423.00 | $0.00 | $24,423.00 |
| RF Sons Engineering | $22,679.10 | $0.00 | $22,679.10 |
| COMBINED TOTAL | $47,102.10 | $0.00 | $47,102.10 |
| Less: Tender Allowance (Item 5.1.1A.7.1) | ($47,565.00) | ||
| ESTIMATED VARIANCE (Actual Cost Method) | ($462.90) | ||
Note: The variation claim uses the proportional method ($40,430.25) based on EW-11A/EW-31 scope increases.
This cost tracking section shows actual expenditure for internal monitoring and forecasting purposes.
| Station | RFT Piles | IFC Piles | Pile Increase | Retaining Walls |
|---|---|---|---|---|
| Glen Innes | 25 | 29 | +16% | 2 |
| Takanini | 33 | 54 | +64% | 11 |
| Te Mahia | 44 | 46 | +5% | 6 |
| TOTAL | 102 | 129 | +26% | 19 |